Chapter 5
Urgency of acquisition
5.1
At the time the Minister for Defence announced the tender arrangements
for the two replenishment ships, he noted the important role of these ships. He
said that replenishment vessels were 'essential to support sustained naval
deployments'. Indeed as noted earlier, the capability provided by the supply
ships enable the rest of the naval fleet to remain at sea for longer periods
and to operate in areas far removed from its base. This capability is referred
to as a 'force multiplier' and is considered an important part of the Navy's
ability to meet its primary objective—'to be able to fight and win in the
maritime environment'.[1]
5.2
The Minister for Defence indicated, however, that both ships were
approaching the end of their useful life: that HMAS Success was in
urgent need of replacement and HMAS Sirius provided only limited
replenishment capability.[2] He stated further:
HMAS Success was commissioned in 1986, this ship
should have been transitioned out of service much sooner than now and, if
you’re familiar with the bathtub curve, the costs of running that particular
replenishment ship are climbing, climbing very high and are very burdensome for
the Navy.[3]
5.3
In his announcement, the Minister cited 'the urgent need to forestall a
capability gap in this crucial area' as one of the main reasons for having the
restricted tender.[4]
According to the Minister, competition between the two experienced ship
builders would be 'the best way to ensure delivery of capable, cost effective
vessels in the time frame required'.[5]
5.4
Mr King supported the view that the ships needed to be replaced. He
noted the requirement for at least three programs to be underway relatively
quickly—the Future Frigates program, the AORs, and Pacific patrol boats. He
indicated that the most urgent and highest priority was the AOR replacement for
the Navy citing the age of Success whose life of type expires in 2016. [6]
5.5
In Mr King's assessment, if Success continued beyond 2017, which
it would have to do, 'every year will get more expensive and more difficult'.[7]
He noted that Defence was already spending a considerable amount of money to
keep the old ship afloat. He also referred to the bathtub curve effect:
When you buy something you have early failures, then you use
it for a large number of years pretty efficiently with limited maintenance, and
then towards the end of its life it seems to become very old and in fact parts
are not even replaceable. In terms of our ships they can be 35 years old.
Imagine getting a pump that is 35 years old. Success is well and truly
into that part of its life.[8]
5.6
Indeed, between 2010 and 2012, HMAS Success underwent significant
maintenance over a 16 month period, which included an IMO requirement to
complete a double-hulling process and the completion of a long standing
propulsion alignment issue. Also, a significant amount of emergent work, consistent
with a ship of this age, has been carried out. The expenditure on HMAS Success
during the period December 2010 and April 2012 was:
December 2010–April 2011 |
IMO Hull Conversion |
$17.8M |
June 2011–November 2011 |
Maintenance Period |
$13.8M |
December 2011–April 2012 |
Propulsion Alignment and ongoing Maintenance |
$4.1M (budgeted at April 2012) |
5.7
In addition to maintenance and repair costs, the Department received
advice in 2012 indicating that 'extending the life of HMAS Success for
five years beyond the current Planned Withdrawal Date of 2018 would require
expenditure just in excess of $20M'.[10]
Mr King spoke of the three possible options:
-
an offshore build, which is the option that Defence is taking;
-
a complete onshore build; and
-
a hybrid build, as with the LHD, with the bulk of the ship
produced in Spain and elements of it fitted out in Australia.[11]
5.8
Mr King stated that the urgency associated with acquiring the two supply
ships reflected the balancing of the complete suite of Defence's need against
the budget and 'when you can afford to embark on programs'.[12]
He then explained:
The quickest replacement time that we think is even remotely
possible is about 3½ years build time—that sort of order. So we need to get
into contract soon. Not only are these needed for military capability, but
every year...Success...is not replaced is an increased maintenance cost that
is likely to accelerate. It is beyond its design life in 2016. Even at the
moment, we are offering 2017. So that is the principle behind it.[13]
5.9
Although noting that Defence sometimes has a capability gap due to a
lack of funds, Mr King would not be drawn on whether a capability gap existed
in respect of the supply ships. He stated that such a matter was getting well
beyond his 'spectrum
of business', which was 'to pursue acquiring products and so on'. He stated:
In terms of whole capability planning, where the money is
spent and when, that is really better handled by Defence more broadly. But
there is a reality: countries haven't the money, Defence has needs and they
have to be balanced off.[14]
5.10
Witnesses agreed that Defence and industry had been aware of the need
to replace the supply ships for years. For example, according to the AMWU, some
of its members working on HMAS Success, understood that the ship was
getting old, was becoming increasingly more expensive to maintain and needed to
be replaced soon.[15]
The Australian Business Defence Industry also referred to the imperative to
replace the ships, which were near or at their end of operational life.[16]
Likewise, Mr Dunk recognised that there were problems with Success and Sirius
regarding their longevity. The Navy League of Australia similarly acknowledged
that one of the main drivers
to call a limited tender from the two overseas shipyards stemmed from the
pressing need to replace the two supply ships. It noted that plans to replace
HMAS Success had been around for some time but the passage of time
without further action had led to the urgency:
HMAS Success is now 28 years old and at an age when
she would normally be replaced. It is believed that the ship is now more
difficult to support as her equipment ages and its reliability reduces. She has
recently completed a major refit. It is understood that further work is planned
to address equipment deficiencies to enable the ship to remain in service until
a replacement can be acquired. [17]
5.11
The League also referred to HMAS Sirius, which, although
relatively new, is a converted commercial tanker that, in its view, 'lacks the
comprehensive support capability provided by HMAS Success'.[18]
Timing and schedule
5.12
No one denied that the Navy needs replenishment ships to service the
rest of the fleet and that their replacement was overdue. Even so, a few
witnesses had proposals that, in their view, would maintain the afloat support
capability and not cause significant delay to the acquisition of the vessels.
5.13
While Mr Christopher Burns, Defence Teaming Centre, acknowledged that
no-one had put forward a proposal to build the whole vessel in Australia, he
noted that two proposals for a hybrid build had been submitted.[19]
For example, as noted earlier, BAE systems informed the committee that it had
submitted an unsolicited proposal to government in September 2012 setting out a
hybrid build program, with part of the ship built overseas and part of the ship
built in Australia.[20]
It estimated that the additional time required producing the replenishment
ships according to its proposed hybrid model would be approximately six months.[21]
5.14
Mr King told the committee that even in informal discussions no company
had suggested to him or his organisation that this ship should be built in
Australia—a partnership though was different. Mr King informed the committee
that he was aware of an unsolicited proposal from BAE for a hybrid build.[22]
Returning to the matter of timing, however, Mr King argued that hybrid builds
or Australian builds introduce complexity and pressure on schedule. He
explained that he worked on the broad principle that:
...if we buy offshore, it comes on time; if we do hybrid; it
comes a bit late; and if we do totally onshore, it is late. That is the basic
premise.[23]
5.15
He used the LHD as an example, noting that the vessel was supposed to be
delivered months ago but was still late by seven months. He explained further
that the builders had all the time they wanted to construct that ship:
I have to make judgements over the top of a commercial
proposal...On an LHD there were 30,000 man-hours of work left over that Navantia
did not do. It cost 70,000 hours in Australia. I have to put forward a degree
of credibility, and for someone to propose that a hybrid build would add only
six months is not credible. I spend most of my time trying to explain to the
public why the AWD is late, why the LHD is now seven months late. And it is
because we get more ambitious than we are able to deliver. I would like to see
an industry that can deliver.[24]
5.16
While stating clearly that it was not credible to suggest that the ship
would only take an additional six months to deliver, Mr King indicated that he
had subsequently received 'other unsolicited offers for offshore builds, which offered
different numbers'.[25]
He told the committee that he did 'not put a lot of confidence in any
unsolicited proposals'.
5.17
When asked why Defence did not go to an open tender in order to test the
claims being made about the various options and the potential to meet the
challenges of the build, Mr King agreed that a tender process would test such
claims, but went on to explain that the actual tenders:
...typically, tend to be wrong, at least in schedule. The point
I have made on many occasions...is that since 2000 our Defence procurement has
run seven per cent under budget. So, typically we get budget right. Our
schedule is about 35 per cent later than we advertised. It is getting better,
but I can assure you that if I relied on unsolicited information we would be
getting worse again. So, you are right: we do go to tender. Even then, though,
we still make judgements.[26]
5.18
Mr King noted further that the main considerations centred on
capability, time and cost.[27]
According to Mr King, he was regularly chastised by members of parliament and
the public and by journalists about projects being late when he had relied on
industry giving him time and cost. He told the committee:
...over and over again, I rarely hear that industry is being
criticised for that misjudgement; it is me. So we have learned to modify, if
you like, industry claims about what they think on that.[28]
5.19
Based on his recent experience in a couple of Asian shipyards, Mr King
told the committee that they have 'not missed a delivery for years, and they
talk about three weeks as being a terrible error. We are talking about years'.[29]
He noted that countries around the world 'can build these ships well'.
Lease vessel
5.20
The AMWU was of the view that Defence had options other than the current
proposal for a limited tender for the supply ships and that an open tender
should have been on the table.[30]
Mr Thompson, AMWU, informed the committee that in 2013,
the union recommended that Defence investigate interim solutions to deal with
Navy's requirement for replenishment vessels. The union proposed leasing a ship
to temporarily replace Success, as Defence had previously done with the Cantabria
when upgrade work was being done on Success. Mr Thompson suggested that
the lease replacement may be for five to eight years, depending on how quickly
an Australian project could be approved.[31]
He reasoned:
This would take the interim schedule pressure off building
the new ship and provide the opportunity to build new ships in Australia. A
hull block could be built in different shipyards. A ship could be consolidated
in Perth, Adelaide or wherever, subject to investment.[32]
5.21
The union was of the view that the circumstances of Sirius were
not as urgent.[33]
It noted that while the Sirius was an Auxiliary Oiler and not an
Auxiliary Oiler Replenishment like Success, there was no pressing need
to replace the ship because of its age or cost to maintain. It conceded that while
it may be ideal to get
the additional capability and replace the ship early, by 'all accounts, Sirius
has served the Navy well for the past eight years'.[34]
5.22
According to Mr Thompson, if there were no interim option, there could
be another solution, which would entail a hybrid build of ship 1 while sending
Australian shipbuilders to that shipyard to learn. Then:
Ship 2 could be built in Australia, using this as an option
to invest in the Australian capability and help bridge the gap between the
current and future work.[35]
5.23
The option of leasing a vessel, as done previously, was put to Mr King
who indicated that that arrangement had been a 'one-off, special arrangement'
and that ultimately Defence had to purchase the replacement ships. He indicated
that leasing a vessel or acquiring a second-hand AOR was considered and
determined not to be feasible.[36]
According to Defence, open market research revealed that there were no suitable
vessels evident on the world market to purchase as a second hand AOR.
Furthermore, that:
Defence engagement, primarily through navy-to-navy contacts,
with allies for the prospect of leasing an in-service foreign navy AOR was also
unsuccessful, with no suitable leasing options identified.[37]
5.24
Mr King informed the committee that Defence had, for several years,
been working on this problem, working through options.[38]
Conclusion
5.25
The committee understands the need to purchase the replacement
replenishment ships to avoid a capability gap and to stem the continuing costs
of maintaining an ageing vessel. The urgency of this situation highlights the
need for government to have a realistic and practical long term capability
plan.
5.26
A number of witnesses have put forward proposals that could address this
potential shortfall in capability but without having to resort to a limited
tender.
They include a hybrid build with a slightly longer schedule or finding a
temporary replacement by leasing a vessel. Defence indicated that leasing a
vessel or purchasing a second-hand one were not viable options. Even so, the
committee is concerned that the pressing need to acquire the vessels has led to
a decision that effectively closes down options and prevents a more open,
competitive and, indeed, fairer process.